Project Overview
Starting May 3, the City of East Wenatchee will begin construction on 10th Street NE from Eastmont Ave to Kansas Ave. The City will be adding sidewalks, illumination, bike lanes, parking and repaving the roadway. Utility upgrades include upgrading the stormwater system, replacing aging irrigation lines and water line upgrades through partnerships with Greater Wenatchee Irrigation District and the East Wenatchee Water District. Construction is expected to be completed by late fall 2021.
May 3rd-17th - Detour Information
Local access only on 10th Street, between Eastmont to Grover and Grover to Iowa.
The intersection at N Grover and 10th Street will be open to traffic crossing 10th Street.
More detours are expected throughout this project and all of those details will be posted here. If you have any questions or concerns please contact the City of East Wenatchee at 509-884-1829 or by emailing the Project Development Manager.
Detour Map