Posted on: May 20, 2021

10th Street Detour

Detour Road Signs in the middle of empty road.

Project Overview

Starting May 3, the City of East Wenatchee will begin construction on 10th Street NE from Eastmont Ave to Kansas Ave. The City will be adding sidewalks, illumination, bike lanes, parking and repaving the roadway. Utility upgrades include upgrading the stormwater system, replacing aging irrigation lines and water line upgrades through partnerships with Greater Wenatchee Irrigation District and the East Wenatchee Water District. Construction is expected to be completed by late fall 2021.

More detours are expected throughout this project and all of those details will be posted here. If you have any questions or concerns please contact the City of East Wenatchee at 509-884-1829 or by emailing the Project Development Manager.

June 14-21: Detour Information

Local Access only on 10th Street, between Eastmont to Iowa and Jennifer to 8th Street.
Local Access only on Grover, between 8th Street NE and 10th Street.

Detour Map (PDF)

Map of 10th Street Detour for June 14-21. Map info is written out on Detour News Flash.

May 17-21: Detour Information

Local access only on 10th Street, between Eastmont to Grover and Grover to above Iowa.
The intersection at N Grover and 10th Street will be open to traffic crossing 10th Street, the intersection at 10 Street and Iowa will be closed to through traffic.

Detour Map (PDF)


May 3-17: Detour Information

Local access only on 10th Street, between Eastmont to Grover and Grover to Iowa.
The intersection at N Grover and 10th Street will be open to traffic crossing 10th Street.

Detour Map

A map of the city showing that 10th Street is for local access only, May 3 through 17, 2021.


Additional Info...
Facebook Twitter Email

Other News in Public Works

Grant Road Detour Signs

Grant Road Detour

Posted on: June 3, 2021
QR Code to the Corridor Study website

SR 28 Corridor Study

Posted on: May 25, 2021